Block C internal lane carpeting extended
Carpeting completed across the majority of Block C internal lanes. Outer streets remain scheduled, with kerb work running ahead of the asphalt crew.
Registered consultants & builders — MPCHS & Faisal Town · Serving Islamabad since 2008
Dated notes from the ground, not a developer's progress bar. Filter by roads, utilities, possession, amenities or balloting.
Executive Block
Possession deliveredBlock A
Partial possessionPrime Block
Under developmentBlock B
Partial possessionBlock C
Partial possessionBlock D
Possession deliveredCarpeting completed across the majority of Block C internal lanes. Outer streets remain scheduled, with kerb work running ahead of the asphalt crew.
Main sewerage lines are laid along both spine roads in Block D. Lane-level connections continue in sequence from the block entrance inward.
All Executive Block streets are now on the society lighting circuit, completing the last outstanding item for the block.
Formation and sub-base work started on the Prime Block northern spine. This is the milestone that typically precedes lane-level development in a new release.
The Block B central park irrigation network has been replaced, with new planting along the walking track and additional seating installed.
Possession handed over for the second arcade on the main boulevard inside Executive Block. Ground-floor units are letting; upper floors remain largely vacant.
The Prime Block access road now connects to the northern spine, opening site access for development machinery.
Possession is now available across most Block A sectors. A handful of outer lanes remain on a street-level check before a token — the civic centre and the bulk of the residential grid are handed over.
If you are buying in a developing block, we will take you to the spine road and the plot. That visit answers more than this page can.